Last Updated on May 15, 2017

The EMS bay is nearing completion and now has a roof on it.  The WT trailer has been removed and replaced by a smaller one in the back to begin grading for the parking lot.  The bridge continues to develop and you can begin to see clean up around the jobsite as well as further grading around the perimeter of the building in preparation for landscaping.