Building 6
Substantial completion end of June, 2017
Staff relocated by end of August, 2017
Phase 1
RGT building demo completed: Mid-April, 2017
Install temporary RG entrance completed: End of May, 2017
Construction : July 2017 through October, 2018
Licensing complete: End of December, 2018
Occupancy: End of January, 2019
Phase 2
RG South building demo completed: End of April, 2019
Construction: May, 2019 through June, 2020
Occupancy: End of September, 2020
Final sitework/landscaping: End of February, 2021
Dates are subject to change.